Latest April Photo Feature showing on-going work to complete Camogli Healthcare Centre

Latest Heathcare Centre Construction Update

Photo Report from Clerk of Works Barry Davies on 25th April 2017

To date Tristan has had 264mm (10.5 inches) of rain in April which has caused widespread flooding. Nevertheless, Galliford Try contractors have continued to make good progress and have entered the final phase of the project. Nine construction staff are expected to leave Tristan da Cunha on 18th May 2017 and Galliford Try is expected to make timely completion and handover of the project by mid June 2017.

  

Left: Circulation area by the entrance; Right: Electricians Martin Attwood& Zlatko Goodwin-Izmirov

  

Left: Main Entrance; Right: John Sanders, Les Jones and John Taylor

  

Left: Multi-function room internal wall cladding; Right: North side

  

Left: Operating Theatre; Right: West Side