Pre-fabrication of the Camogli Healthcare Centre in SwedenClerk of Works for the project Barry Davies, now returned to Tristan preparing for the ship to arrive, visited Sweden in May 2016 and has sent the photo below showing construction of the pre-fabricated sections of the new Camogli Healthcare Centre. |
|
Pre-cast foundation steel moulds c/w reinforcement prior to casting | Completed pre-cast foundation pads prior to transferal to Malmo Port warehouse |
Ongoing floor cassette production/dispatch to port warehouse | Completed floor cassettes at port warehouse weather protected for shipping |
Roof truss production for new health facility | Fabrication steel grillage prior to galvanising treatment |
Delivered windows in readiness for external wall panel production | Fabrication of Hygiene Area Plant Room |
Inset drainage to floor cassettes | Fabrication of main Plant Room |
AHU equipment for Plant Room installation | Fit out of Plant Room 1 |